Lift Service

Communication of commissioning and assignment of serial number

Following the communication of commissioning, the Lift Office, after having checked the documentation presented, assigns the serial number for the lift systems, goods lifts and lifting equipment that meet the definition of lift, in private service.

In the cases provided for by the articles. 13 (paragraph 2), 14 (paragraph 1 and 2), 15 (paragraph 7) of Presidential Decree 162/99 the Office can adopt repressive measures.

It is possible to late transmit to the Municipal Administration the communication of commissioning for the aforementioned systems according to the procedures defined with the note of the Ministry of Economic Development - Prot. 0069816 of 24.04.2013.

Request


Communication of commissioning of the system

Starting from 22 April 2024, communications for the commissioning of the plants must be submitted by completing the online form.

The communication of commissioning of lifts, hoists and lifting equipment falling within the definition of lifts (provided for by art. 12 of Presidential Decree 162/99) must be made by the owner of the property or his legal representative.

Before accessing, check that you have the mandatory documentation that must be attached during the procedure:

  • If the applicant is a delegate: copy of the identity document of the owner and/or authorized person and digitally signed delegation
  • EU declaration of conformity referred to in art. 4 - bis, paragraph 2, Presidential Decree 162/99 or the EC declaration of conformity referred to in art. 3, paragraph 3, letter e), Legislative Decree 27 January 2010 n. 17.
  • Declaration of acceptance of the assignment to carry out maintenance
  • Declaration of acceptance of the assignment to carry out periodic checks
  • Extraordinary verification report of the activation of the system carried out by the competent notified body appointed by the owner if the communication of commissioning is made after the deadline of 60 days from the date of the declaration of conformity of the system.

The payment of €100 due for Secretarial Fees must be made via PagoPa and will be requested when filling out the form.

All attached documentation must be digitally signed.

Negative report submission (reserved for notified bodies)

Access the service to forward the negative report following a biannual periodic visit.

Note the attached documentation must be digitally signed.

Sending supplementary documents - Communication of construction changes

It is only possible to send supplementary documentation relating to procedures already started explicitly requested by the office and communications of construction changes to the following PEC address: sueAscensori@pec.comune.milano.it 

 

For information requests you can send an email to:  SueAscensori@comune.milano.it

  • Presidential Decree 162/99
  • Note from the Ministry of Economic Development - Prot. 0069816 of 24.04.2013 relating to the plants referred to in art. 19 of Presidential Decree 162/99

Updated: 22/04/2024